We strive to provide our customers with the most accurate and up-to-date information regarding our manufacturing lead times. This information is made available to help you plan your projects effectively and ensure timely delivery of our specialized products. We understand the importance of reliable timelines and aim to serve you best by offering transparency in our production schedules.
Lead times, measured in weeks, reflect the production time from approved submittals to when the product is ready for shipment.
Last Updated: October 1st, 2024
Factors Impacting Lead Times
Multibank > 1 and quantity >10: +1 week
Quantity >40 +1 week
Quantity >80 +2 weeks
Recessed panels:
1-5 Panels +2 weeks
5-15 Panels +4 weeks
15+ Panels consult
Lite Kits
<5 +1 week
Acoustic Lead Times
Product
Submittals
Frames
Steel Doors
Wood Doors
Up to STC 51
2
7
9
11
STC 52-56
2
7
10
13
STC 59
2
10
16
N/A
Safety & Security Lead Times
Product
Submittals
Frames
Steel Doors
Wood Doors
Bullet Level 1-3
3
7
9
10
Bullet Level 4+
3
10
27
17
Forced Entry
3
10
27
N/A
Anti Barricade
3
10
N/A
13
Radio Frequency
3
10
14
15
Lead Lined
3
10
10
13
Blast (non structural core)
3
7
10
N/A
Blast ( structural core)
3
10
27
N/A
Combination
3
Consult
Consult
Consult
Climate Resilience
Product
Submittals
Frames
Steel Doors
Wood Doors
Flood
3
7
27
N/A
Tornado
3
7
9
10
Other Products
Product
Submittals
Frames
Steel Doors
Wood Doors
Oversized
4
10
27
17
Brass Clad
4
15
20
N/A
Recessed Panel
4
N/A
10
N/A
Overhead Doors
5
N/A
Consult
N/A
Stainless
3
10
14
N/A
If you have any questions or need further considerations that are not detailed in the posted lead times tables, please do not hesitate to contact us for more information. Our capable team is here to assist and provide the support you need.